Allied Telesis AT-FS705LE Guide d'installation Page 27

  • Télécharger
  • Ajouter à mon manuel
  • Imprimer
  • Page
    / 46
  • Table des matières
  • DEPANNAGE
  • MARQUE LIVRES
  • Noté. / 5. Basé sur avis des utilisateurs
Vue de la page 26
AT-FS705LE Installation Guide
13
6. Attach the data cables to the switch ports. Do
not use a crossover cable to connect
workstations or servers to ports 1 through 5.
Do not use a crossover cable to connect
another switch or hub to the Uplink port.
Note
You can use either Port 5 or the Uplink
port, but you cannot use both
simultaneously.
7. Power ON the end-nodes.
8. Check that the LINK/ACT LEDs for each port
on the switch are green. If the LEDs are OFF,
refer to Troubleshooting on page 16 for
instructions.
The switch is now ready for use.